New York City Transit

JTTC - 137th St EV 520

Specialty
Public Accessibility

About

Project Start: (Estimates Sent) - January 2025

Project Completion: (Delivery & Installation) - November 2025

Company Name: JTTC

Customer Name: Robert Stepien - Project Manager

Project Name: 137th St EV 520

New York City Transit

Results

The installation proceeded exactly as planned, with all five sections fitting together precisely as designed. The modular precast approach significantly reduced onsite labor requirements, compressed the construction schedule, and minimized disruption within a challenging urban environment. The owner and contractor were highly satisfied with both the quality of the finished structure and the efficiency of the installation process. By shifting most of the construction from the jobsite to DVP's manufacturing facility, the project demonstrated the significant advantages precast concrete offers over conventional cast-in-place construction for complex vertical infrastructure applications.

Conclusion

The New York City Transit Elevator Shaft project demonstrates the versatility and value of precast concrete in solving complex infrastructure challenges. Through engineering precision, quality manufacturing, and collaborative execution, DVP delivered a durable, watertight structure that exceeded customer expectations while showcasing the speed, safety, and long-term performance advantages of precast construction. This project serves as another example of how DVP partners with owners, engineers, and contractors to turn challenging concepts into successful, buildable solutions.

Executive Summary

Deihl Vault & Precast (DVP) partnered with the project team at JTTC to manufacture and deliver a custom five-piece precast concrete elevator shaft for a New York City transit accessibility project. Designed as a replacement for traditional cast-in-place construction, the precast solution provided exceptional dimensional accuracy, accelerated construction, reduced onsite labor, and delivered a durable, watertight structure. Manufactured under controlled plant conditions and installed in a single coordinated operation, the project demonstrated how precast concrete can simplify complex infrastructure while improving quality, safety, and schedule performance.

Background

As transit agencies continue investing in accessibility improvements throughout aging infrastructure systems, project teams are challenged to complete work within highly congested urban environments while minimizing disruption to the public. Elevator shafts present unique construction challenges due to their vertical geometry, tight dimensional tolerances, and the need to coordinate multiple trades within limited work windows. Traditional cast-in-place construction often requires extensive forming, reinforcing, curing, and field labor, all of which can extend schedules and increase project risk.

Recognizing these challenges, the project team elected to utilize a precast concrete solution. DVP manufactured the elevator shaft as five custom-engineered sections designed for rapid assembly while maintaining the structural integrity and precision required for the elevator system. Every section was produced under controlled manufacturing conditions, ensuring consistent concrete quality, accurate dimensions, and superior workmanship before ever leaving the plant.

To maximize long-term durability, the structure incorporated Concrete Sealants CS-1800 exterior protective coating together with CS-231 and CS-102 joint sealants to provide a proven watertight system. The modular design also simplified transportation into New York City and allowed the shaft to be efficiently assembled onsite using crane installation, dramatically reducing field construction activities compared to traditional methods.

partnering with pennsylvania's leading companies

Customer testimonials

"Deihl Vault and Precast has been a critical partner with us in our formation and growth. They consistently keep communication open between estimating, accounting, and dispatch staff. Beyond timely production and delivery to any job we work, their knowledge and insight has proved invaluable to us and our clients. Proper planning is the key to succeeding at any job, no matter the size and scope. The experienced staff at Deihl Vault and Precast always strive to make our life easier and contribute to the success of a project before it ever starts. We have never gone wrong partnering with DVP."